Wudongde Hydropower Station has generated 21.528 billion kwh of clean electric energy
at 16:38 on May 2 and 16:35 on May 3, units 11 and 2 of Wudongde Hydropower Station completed 72 hour trial operation respectively and officially put into commercial operation. Wudongde Hydropower Station has a total of 12 units. So far, 10 units have been successfully put into operation for power generation, which is another solid step towards putting all units into operation for power generation before July 1
at 16:38 on May 2 and 16:35 on May 3, units 11 and 2 of Wudongde Hydropower Station have completed 72 hour trial operation respectively, otherwise they will be passively officially put into commercial operation. 4. They will operate through wireless remote control box. Wudongde Hydropower Station has a total of 12 units. So far, 10 units have been successfully put into operation for power generation, which is another solid step towards putting all units into operation for power generation before July 1
2 and 11 units completed rotor hoisting on January 25 and January 28, 2021 respectively, and completed general assembly and water free commissioning in early April. With the consent of the unit startup Acceptance Committee, they were first started on April 16 and 15, respectively. The mechanical and electrical installation and commissioning team of the Ministry of engineering and construction of Wudongde carefully organized each test. After 19 days and nights of continuous struggle, more than 30 tests and thousands of operations for the startup and commissioning of each unit were completed accurately, and all test items passed at one time The vibration, swing, temperature and other operating parameters of units 2 and 11 are all better than the standard requirements of high-quality units of the Three Gorges group, and the operation quality is further improved
it is understood that the first eight units of Wudongde Hydropower Station have all passed the "first stable hundred days" assessment in March 2021. As of May 3, Wudongde Hydropower Station has delivered 21.528 billion kwh of clean electric energy, which shows the experimental data and results. The developed experimental machine products have contributed to the implementation of the "six guarantees" and the "six stabilities" for China's economic development
LINK
Copyright © 2011 JIN SHI